Golden Avenue Bridge project cost increase

Placentia

Summary

Utility delays pushed the Golden Avenue Bridge project past its original schedule, so the council added $302,848 to T.Y. Lin's construction management contract. Completion is now expected November 22, 2026.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 8, 2026.

Impact analysis

💰Financial impact

Adds $302,848 to the construction management contract, raising it to $1,015,939.

✅Who benefits

Bridge users and the broader traveling public once the project completes.